Recently, the TETELO Copper Mine—Angola's first large-scale non-ferrous metal mine—successfully commenced production. KE Electric's 114 sets of complete switchgear products were successfully deployed in this large-scale overseas industrial project. With 106 days of on-site O&M support throughout the entire project lifecycle, KE Electric not only ensured stable equipment operation but also earned high recognition from the owner through technical problem-solving and service upgrades, building a reliable brand image for "Created in China" in the African market.

 

106 Days of Overseas Endeavor: KE Electric Supports Angola Copper Mine Project to Successful Commissioning

 

As critical power equipment for Angola's first large-scale non-ferrous metal mine, the KYN28A-12 high-voltage switchgear is engineered for Africa's complex conditions—high temperatures, high humidity, and grid fluctuations. With moisture-proof, mold-proof, and salt-spray-resistant "three-proof" capabilities, and certified to withstand 50kA short-circuit breaking and 1-second arc impact testing, it ensures power stability for the mine's core production processes. The MNS low-voltage switchgear adopts high-strength flame-retardant components with an IP40 protection rating, providing a dual layer of safety for power supply.

 

The intelligent monitoring system integrated into the equipment supports remote data collection, fault warning, and mobile terminal interaction, enabling full visualization of equipment status and ensuring long-term, highly reliable smart operation. The modular design further enhances deployment efficiency and significantly shortens on-site commissioning cycles, providing strong support for efficient project advancement.

 

106 Days of Overseas Endeavor: KE Electric Supports Angola Copper Mine Project to Successful Commissioning

 

KE Electric's professional O&M team traveled to Africa and overcame multiple challenges within 106 days to efficiently complete the entire process of installation, commissioning, and power-on. Facing the combined pressures of additional orders, tight schedules, and harsh environmental conditions, the engineers responded quickly and successfully delivered power on schedule, successfully completing the assigned tasks. The team also proactively assisted the owner in resolving technical issues beyond their contractual responsibilities, earning praise for their spirit of "exceptional resilience and dedication."

 

106 Days of Overseas Endeavor: KE Electric Supports Angola Copper Mine Project to Successful Commissioning

 

The success of this project not only demonstrates the reliable quality of KE Electric's products but also highlights the company's full-chain strength from R&D to on-site service, providing stable power support for the TETELO Copper Mine in Angola and contributing to local economic development.

 

Going forward, KE Electric will continue to safeguard more projects worldwide with professional technology and quality service, writing new chapters of "Created in China" success in overseas markets.

Previous:

KE-5130/5150 100-208kWh All-in-One PV & Storage Cabinet for C&I Applications

Next:

YB(H)-40.5/0.4kV~1.14kV New Energy Intelligent Step-up Box Substation (European/Chinese Type)

Find Solutions, Not Just Suppliers

If you are interested in any of our products or would like to make your customized order, please feel free to contact us. We are looking forward to establish successful business relations with you.

Discover More